Which of the following BEST describes the information that a Work Breakdown Structure (WBS) provides to the project team?

  • It is a hierarchical decomposition of the total project scope into deliverables and work packages without showing activity sequencing.

  • It illustrates the critical path and total float for each task in the project timeline.

  • It shows the sequence of project activities and their interdependencies to build the project schedule.

  • It allocates resources and budgets to each activity in order to control project costs.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot