Which of the following BEST describes the function of a Work Breakdown Structure (WBS) in project management?

  • It allocates project resources to specific tasks.

  • It sequences project activities in the order they will be performed.

  • It provides detailed scheduling of project activities.

  • It organizes project deliverables into manageable sections.