CAPM Practice Question
Which of the following artifacts provides a hierarchical outline of all project deliverables in a predictive, plan-based project?
Quality Management Plan
Stakeholder Register
Risk Register
Work Breakdown Structure
Which of the following artifacts provides a hierarchical outline of all project deliverables in a predictive, plan-based project?
Quality Management Plan
Stakeholder Register
Risk Register
Work Breakdown Structure
The Work Breakdown Structure (WBS) provides a hierarchical outline of all project deliverables in a predictive, plan-based project. It breaks down the project scope into smaller, manageable components, ensuring that all aspects of the project are accounted for and organized systematically. The Risk Register documents potential risks and mitigation plans but does not outline deliverables. The Quality Management Plan details quality standards and processes but does not offer a hierarchical structure of deliverables. The Stakeholder Register identifies all stakeholders and their interests but does not relate to the project's deliverables or their organization.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.