CAPM Practice Question

Which of the following artifacts is typically associated with agile methodologies, rather than predictive, plan-based projects, for tracking progress?

  • Work Breakdown Structure (WBS) dictionary

  • Gantt chart

  • Critical path network diagram

  • Burndown chart

CAPM
Predictive, Plan-Based Methodologies