CAPM Practice Question
Which of the following activities is typically performed during the project closure phase?
Creating a stakeholder engagement plan
Updating the quality management plan
Documenting lessons learned
Performing variance analysis
Which of the following activities is typically performed during the project closure phase?
Creating a stakeholder engagement plan
Updating the quality management plan
Documenting lessons learned
Performing variance analysis
Documenting lessons learned is a key activity during project closure as it captures valuable insights and experiences from the project, which can be used to improve future projects. Other activities like creating a stakeholder engagement plan, performing variance analysis, and updating the quality management plan are typically done during planning and execution phases.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.