CAPM Practice Question
Which of the following activities is typically performed during the Closing process group in project management?
Defining project scope
Managing the project team
Formally accepting project deliverables
Performing risk analysis
Which of the following activities is typically performed during the Closing process group in project management?
Defining project scope
Managing the project team
Formally accepting project deliverables
Performing risk analysis
Formally accepting project deliverables is a key activity in the Closing process group. This involves obtaining stakeholder or customer approval that the project deliverables meet the agreed-upon requirements. The other options are associated with different process groups: defining project scope is part of the Planning process group, managing the project team occurs during the Executing process group, and performing risk analysis is conducted during the Planning process group.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.