CAPM Practice Question
Which document provides the project manager with authority to utilize organizational resources for project activities?
Project Scope Statement
Organizational Process Assets
Project Charter
Project Management Plan
Which document provides the project manager with authority to utilize organizational resources for project activities?
Project Scope Statement
Organizational Process Assets
Project Charter
Project Management Plan
The Project Charter provides the project manager with the authority to utilize organizational resources for project activities. It is the document that formally authorizes the existence of the project. The Project Management Plan describes how the project will be executed and controlled but does not confer authority. The Project Scope Statement details the project's deliverables and scope but does not grant authority. Organizational Process Assets are company policies and procedures, not documents that authorize resource use.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.