CAPM Practice Question
Which document is BEST used to record and manage project controls in a predictive, plan-based project?
Stakeholder Register
Risk Register
Project Management Plan
Issue Log
Which document is BEST used to record and manage project controls in a predictive, plan-based project?
Stakeholder Register
Risk Register
Project Management Plan
Issue Log
The Project Management Plan is the primary document that outlines how a project will be executed, monitored, and controlled. It includes subsidiary plans and baselines necessary for controlling the project scope, schedule, cost, quality, and more. While the Risk Register, Issue Log, and Stakeholder Register are important documents, they focus on specific aspects of the project and do not encompass all project controls.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.