CAPM Practice Question
Which approach BEST ensures that project deliverables are thoroughly identified and organized during project planning?
Organizing tasks according to the company's departmental structure.
Focusing on product deliverables and omitting management activities.
Breaking down deliverables into smaller components until they are manageable.
Arranging tasks in chronological order based on the project schedule.