CAPM Practice Question

When converting a Work Breakdown Structure (WBS) into iterations for an adaptive project, what is the key focus when organizing tasks?

  • Organize tasks to complete all documentation before development.

  • Assign tasks based on team members' availability and skill sets.

  • Group tasks to deliver working features that provide incremental value.

  • Distribute tasks evenly to balance team members' workloads.

CAPM
Agile Frameworks/Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot