Sarah is managing a large infrastructure project with multiple teams working on interconnected components. Midway through the project, a key stakeholder requests a significant change to one of the deliverables. What should Sarah do first to address this request?
Evaluate the impact of the requested change on the project's scope, schedule, and cost before proceeding.
Implement the change to keep the stakeholder satisfied.
Seek approval from the project sponsor to increase the project budget.
Reject the change to prevent delays in the project timeline.