A project team is tasked with constructing a pre-designed commercial building. The architectural plans are complete and approved, the client's requirements are fully documented and signed off, and the project environment is considered stable. Which of the following project management approaches is MOST appropriate for this project?
An adaptive approach, because it allows the team to respond to unforeseen construction challenges.
An incremental approach, to deliver functional parts of the building to the client early.
A hybrid approach, to combine the benefits of detailed planning with iterative development.
A predictive approach, because the scope is well-defined and stable.
A predictive, plan-based approach is the most suitable choice. This methodology is designed for projects where the requirements are well-defined, stable, and unlikely to change, such as in this construction scenario. The ability to perform detailed upfront planning for scope, schedule, and cost makes the predictive approach ideal for ensuring the project is completed according to the fixed specifications. Adaptive and hybrid approaches are better suited for projects with higher levels of uncertainty and evolving requirements.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are predictive project management approaches?
Open an interactive chat with Bash
What are adaptive methodologies in project management?
Open an interactive chat with Bash
How do project requirements influence the choice of methodology?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access