Milestones in project management are used to mark the completion of important deliverables and have durations equal to those of the tasks they represent.
True
False
Milestones in project management are used to mark the completion of important deliverables and have durations equal to those of the tasks they represent.
True
False
This statement is false. Milestones are significant points or events in a project timeline that typically have zero duration. They mark the completion of key phases or events but do not have durations like tasks. Instead, they act as markers to signify important moments in the project schedule without impacting the timeline with additional duration.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.