Midway through project execution, a key stakeholder emails the project manager requesting weekly status reports that are not specified in the approved communications management plan. According to PMI best practices, what is the most appropriate next step for the project manager?

  • Explain to the stakeholder that additional updates are not possible.

  • Update the communications management plan to add the weekly reports.

  • Proceed with the existing plan and disregard the new request.

  • Evaluate the request's impact and initiate the change management process.

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot