Maria is managing a project to develop a new smartphone application. The project's activities, their durations in days, and dependencies are as follows:

  • Activity A: 3 days, starts at project commencement
  • Activity B: 5 days, depends on completion of Activity A
  • Activity C: 2 days, depends on completion of Activity A
  • Activity D: 4 days, depends on completion of Activities B and C

What is the shortest possible duration to complete the entire project?

  • You selected this option

    12 days

  • You selected this option

    14 days

  • You selected this option

    9 days

  • You selected this option

    10 days

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot