Maria is managing a project to develop a new smartphone application. The project's activities, their durations in days, and dependencies are as follows:
- Activity A: 3 days, starts at project commencement
- Activity B: 5 days, depends on completion of Activity A
- Activity C: 2 days, depends on completion of Activity A
- Activity D: 4 days, depends on completion of Activities B and C
What is the shortest possible duration to complete the entire project?
12 days
14 days
9 days
10 days