CAPM Practice Question
In project scheduling, which sequence of activities determines the minimum time required to complete a project?
The tasks with the highest resource allocation
The longest sequence of tasks that cannot be delayed without delaying the project
The shortest sequence of tasks in the project
The tasks with the largest budget