In project schedule management, which sequence of activities dictates the project's earliest finish date because delays in these activities will delay the entire project?
The critical path is the sequence of activities that determines the shortest time in which a project can be completed. Any delay in activities on the critical path will directly impact the project's end date because there is zero float. Other paths may have float, allowing for some flexibility without affecting the overall project duration.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is float in project management?
Open an interactive chat with Bash
How do you identify the critical path in a project?
Open an interactive chat with Bash
What happens if a critical path activity is delayed?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .