In project management, which of the following represents a significant point or event in the project timeline with zero duration?
Activity
Milestone
Work Package
Task Duration
In project management, which of the following represents a significant point or event in the project timeline with zero duration?
Activity
Milestone
Work Package
Task Duration
A milestone represents a significant point or event in the project timeline that has zero duration. Milestones are used to mark critical dates, such as the completion of a major phase or deliverable. Option A, a Work Package, is a group of related tasks within a project, not a point in time. Option C, Task Duration, refers to the amount of time required to complete a task. Option D, Activity, is a task or set of tasks that consume time and resources. Therefore, a milestone is the correct answer as it signifies a significant event with zero duration.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.