A work package is a deliverable or project work component at the lowest level of each branch of the Work Breakdown Structure (WBS). It represents a defined piece of work that can be assigned to a person or team and for which cost and duration can be estimated and managed. The other options are incorrect because a grouping of related projects managed together is a program, a detailed schedule of activities describes a project schedule, and assigning tasks to team members pertains to resource allocation, not the definition of a work package.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the Work Breakdown Structure (WBS)?
Open an interactive chat with Bash
Why are work packages important in project management?
Open an interactive chat with Bash
How do work packages relate to project deliverables?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access