CAPM Practice Question
In project management, which of the following best defines a work package?
An assignment of project tasks to individual team members
A detailed schedule of activities and tasks required to complete a project
A grouping of related projects managed together for strategic alignment
A deliverable or project work component at the lowest level of each branch of the Work Breakdown Structure (WBS)