CAPM Practice Question

In project management, which formula is used to determine if a project is ahead or behind its planned schedule?

  • Earned Value (EV) divided by Planned Value (PV)

  • Earned Value (EV) minus Planned Value (PV)

  • Planned Value (PV) minus Earned Value (EV)

  • Earned Value (EV) minus Actual Cost (AC)

CAPM
Predictive, Plan-Based Methodologies