CAPM Practice Question
In project management, which formula is used to determine if a project is ahead or behind its planned schedule?
Earned Value (EV) divided by Planned Value (PV)
Earned Value (EV) minus Planned Value (PV)
Planned Value (PV) minus Earned Value (EV)
Earned Value (EV) minus Actual Cost (AC)