CAPM Practice Question
In project management, what is the term for the smallest unit of work that can be scheduled, cost-estimated, and assigned to a responsible party?
Activity
Work package
Project phase
Milestone
In project management, what is the term for the smallest unit of work that can be scheduled, cost-estimated, and assigned to a responsible party?
Activity
Work package
Project phase
Milestone
The correct answer is a work package. A work package is the smallest unit of work in a project that can be planned and managed. It is a key component of the work breakdown structure and includes specific tasks, resources, and costs needed to produce a particular deliverable. Other options like milestones, project phases, and activities represent different aspects of project management but do not specifically refer to this lowest-level unit that can be assigned and scheduled.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.