CAPM Practice Question
In project management, what is the term for the smallest unit of work that can be scheduled, cost-estimated, and assigned to a single responsible party?
Activity
Project phase
Milestone
Work package
In project management, what is the term for the smallest unit of work that can be scheduled, cost-estimated, and assigned to a single responsible party?
Activity
Project phase
Milestone
Work package
A work package is the smallest unit of work in a project that can be scheduled, cost-estimated, and assigned to a responsible person or team. It represents a specific deliverable and is detailed enough to allow for accurate planning and control. Unlike activities or tasks, which may be components of a work package, the work package itself is a summary of these components and is used for higher-level management within the Work Breakdown Structure (WBS).
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.