CAPM Practice Question
In an adaptive project, which artifact is used to document the team's analysis of their processes and to plan improvements for future iterations?
Retrospective Notes
Burndown Chart
Release Plan
Product Backlog
In an adaptive project, which artifact is used to document the team's analysis of their processes and to plan improvements for future iterations?
Retrospective Notes
Burndown Chart
Release Plan
Product Backlog
Retrospective Notes are used in adaptive projects to document the team's analysis of their processes after each iteration. This artifact captures insights on what went well, what didn't, and how the team can improve in future iterations, fostering continuous improvement. The Product Backlog lists the features and requirements to be developed, the Burndown Chart shows remaining work over time, and the Release Plan outlines the schedule for delivering product increments. While these artifacts are important, they do not specifically focus on analyzing team processes and planning improvements.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.