Iterations in iteration-based adaptive frameworks are deliberately time-boxed to a set duration (often one to four weeks). Using a fixed length establishes a predictable cadence, simplifies planning, and ensures frequent inspection and adaptation. Iterations that vary in length, extend to match scope, or are scheduled only after a release would undermine these agile principles.