Labor Day Flash Sale: 30% off Today Only!

10 hours, 13 minutes remaining!

CAPM Practice Question

A project manager reviewing a network diagram notes that a particular activity has zero total float. What does this signify?

  • The activity requires additional resources to be completed.

  • The activity has a flexible start date.

  • The activity is on the critical path.

  • The activity has been completed ahead of schedule.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot