CAPM Practice Question
If a project's cost variance (CV) is negative, what does this signify?
The project is behind schedule
The project is over budget
The project is under budget
The project is ahead of schedule
If a project's cost variance (CV) is negative, what does this signify?
The project is behind schedule
The project is over budget
The project is under budget
The project is ahead of schedule
A negative cost variance indicates that the project is over budget, meaning it has spent more than planned for the work accomplished. A positive CV would mean the project is under budget, and a CV of zero indicates costs are exactly as planned.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.