CAPM Practice Question
For a project where requirements are well-understood and unlikely to change, which life cycle approach is most suitable?
Incremental life cycle
Adaptive life cycle
Iterative life cycle
Predictive life cycle
For a project where requirements are well-understood and unlikely to change, which life cycle approach is most suitable?
Incremental life cycle
Adaptive life cycle
Iterative life cycle
Predictive life cycle
The predictive life cycle is most suitable when project requirements are well-understood and stable. In this approach, scope, time, and cost are determined early, and changes are carefully managed. Adaptive life cycles are better suited for projects with evolving requirements. Iterative and incremental life cycles are also used when requirements are expected to change.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.