CAPM Practice Question

Emily is managing a project with a planned value (PV) of $40,000 after four weeks. The earned value (EV) at the same point is $35,000. Based on this information, is the project ahead of schedule, behind schedule, or on schedule, and by how much?

  • You selected this option

    The project is ahead of schedule by $5,000

  • You selected this option

    The project is on schedule

  • You selected this option

    The project is under budget by $5,000

  • You selected this option

    The project is behind schedule by $5,000

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot