During your review of the project scope statement, you find that it includes the deliverables, acceptance criteria, constraints, and assumptions but lacks clarity on items that are not part of the project. What should you incorporate into the scope statement to complete it?
Add project exclusions
Include detailed cost estimates
Incorporate organizational process assets
Attach the project charter