CAPM Practice Question
During the project closure phase, which of the following actions should be performed first to ensure a successful transition?
Obtain formal acceptance of the project deliverables from the customer.
Close out all procurement contracts associated with the project.
Conduct a final project performance review.
Release project team members to their functional departments.