During the planning phase of a project, you need to determine the number and type of resources required to complete the project work. Which of the following documents will provide the most detailed information to assist in this task?
The Work Breakdown Structure (WBS) breaks the project into smaller, manageable components called work packages. By analyzing the WBS, you can identify all the deliverables and tasks, which is essential for determining the number and type of resources needed. The Project Scope Statement provides an overview of the project's scope but lacks detailed task breakdown. The Resource Management Plan outlines how resources will be managed but does not specify the detailed resource requirements. The Risk Register identifies potential risks but does not aid in determining resource needs.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a Work Breakdown Structure (WBS)?
Open an interactive chat with Bash
How do I create a Work Breakdown Structure?
Open an interactive chat with Bash
What other documents are involved in project planning?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access