CAPM Practice Question
During the planning phase of a project, you need to determine the number and type of resources required to complete the project work. Which of the following documents will provide the most detailed information to assist in this task?
Risk Register
Project Scope Statement
Resource Management Plan
Work Breakdown Structure (WBS)