CAPM Practice Question

During the planning phase of a complex project, a project manager notices that schedules from different departments are not aligning, leading to potential conflicts and delays. What should the project manager do to address this issue and ensure all project elements are properly coordinated?

  • Implement a quality management plan to improve department performance

  • Adjust the project scope to accommodate the conflicting schedules

  • Develop an integration management plan to coordinate all project plans

  • Increase the project budget to mitigate scheduling conflicts

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot