During the initiation phase of a predictive, plan-based project, which key project management artifact formally authorizes the project and grants the newly assigned project manager authority to utilize organizational resources for planned project activities?
The Project Charter is the artifact that formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. The Project Scope Statement outlines the project scope but does not grant authorization. The Stakeholder Register identifies and documents project stakeholders but does not authorize the project. The Risk Management Plan describes how risk management will be structured and performed but also does not provide any authorization.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is included in a Project Charter?
Open an interactive chat with Bash
Why is the Project Charter created during the initiation phase?
Open an interactive chat with Bash
Who is responsible for creating the Project Charter?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .