CAPM Practice Question
During the execution phase of a project, a key stakeholder requests a significant change to the project scope. How should the project manager respond to this request according to the planned strategy or framework?
Implement the change promptly to address the stakeholder's concern.
Refer the stakeholder to the change control process as specified in the project management plan.
Deny the request, stating that changes typically require approval during execution.
Postpone the decision pending further discussion or review.