CAPM Practice Question
During the execution of a project, the project manager wants to ensure that the deliverables meet the quality standards defined in the quality management plan. Which of the following is the BEST action to achieve this goal?
Update the quality management plan to incorporate new quality requirements.
Implement quality control measures to evaluate deliverables against quality standards.
Assign additional resources to enhance productivity and meet deadlines.
Conduct quality audits to identify and improve ineffective processes.