CAPM Practice Question

During the execution of a project, the project manager wants to ensure that the deliverables meet the quality standards defined in the quality management plan. Which of the following is the BEST action to achieve this goal?

  • Update the quality management plan to incorporate new quality requirements.

  • Implement quality control measures to evaluate deliverables against quality standards.

  • Assign additional resources to enhance productivity and meet deadlines.

  • Conduct quality audits to identify and improve ineffective processes.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot