During the execution of a project, a key stakeholder submits a request that would alter a critical deliverable. The project manager has a documented change management plan. How should the project manager address this request?
Forward the request to the project sponsor for a decision.
Implement the change to satisfy the stakeholder's needs.
Follow the procedures in the change management plan to evaluate and process the request.
Reject the request to maintain the original project scope.
The project manager should refer to the change management plan and adhere to the outlined procedures for processing change requests. This approach ensures that all changes are systematically evaluated for their impact on scope, schedule, cost, and quality before any decisions are made. Implementing the change immediately bypasses the necessary evaluation process and could introduce risks. Rejecting the request without assessment may overlook potential benefits. Escalating directly to the sponsor is unnecessary if the change management plan provides a clear process for handling such requests.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a change management plan in project management?
Open an interactive chat with Bash
Why is it important to follow a change management plan?
Open an interactive chat with Bash
What is the role of stakeholders in the change management process?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .