During the closure phase of a project, all deliverables have been accepted, and the project objectives have been met. The project manager wants to ensure a smooth transition and capture valuable information for future projects. What is the most appropriate action for the project manager to take next?
Release the project team members to their functional managers.
Prepare a final project report and update lessons learned documentation.
Celebrate the project's success with a team event.
Close all project contracts with vendors and suppliers.
The most appropriate action is to prepare a final project report and update lessons learned documentation. This formalizes the project's completion and provides insights that can improve future projects. While releasing team members, closing contracts, and celebrating are important, they do not directly contribute to capturing and transitioning valuable knowledge.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a final project report and why is it important?
Open an interactive chat with Bash
What does 'lessons learned documentation' involve?
Open an interactive chat with Bash
Why is capturing knowledge important at the end of a project?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access