During Sprint Planning on an adaptive project, the team needs an artifact that lists and orders potential work so they can choose what will be delivered in the upcoming iteration. Which of the following artifacts is typically used for this purpose?
A detailed project plan outlining all tasks and activities from start to finish.
A resource allocation matrix assigning team members to tasks throughout the project.
A prioritized backlog of user stories to be addressed in the iteration.
A comprehensive work breakdown structure covering the entire project scope.
In adaptive project management, a prioritized backlog of user stories is used to plan each iteration. This approach lets the team pull the highest-value items first and adjust scope as priorities evolve. The other options correspond to predictive, plan-driven methods and are not the primary planning tools for iterative work.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a prioritized backlog in adaptive project management?
Open an interactive chat with Bash
How is a prioritized backlog different from a work breakdown structure (WBS)?
Open an interactive chat with Bash
Why is flexibility important in adaptive project management?
Open an interactive chat with Bash
CAPM
Agile Frameworks/Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .