During scope planning, a stakeholder asks whether post-implementation training will be part of the project. The project manager notes that this work will be handled by operations and must therefore be documented as out-of-scope. In which section of the project scope statement should this decision be recorded?
Project exclusions explicitly identify deliverables or activities that the team will not perform, setting clear boundaries and managing stakeholder expectations. Acceptance criteria define how completed deliverables will be judged; constraints list limitations such as budget or time; and assumptions capture conditions believed to be true for planning. None of these components state what work lies outside the project's scope.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why are project exclusions important in scope management?
Open an interactive chat with Bash
What is scope creep, and how do project exclusions help prevent it?
Open an interactive chat with Bash
What is the difference between project exclusions and assumptions?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .