CAPM Practice Question
During project planning, detailed estimates of cost and duration are typically made at which level of task decomposition?
The work package level
The project phase level
The activity level
The deliverable level
During project planning, detailed estimates of cost and duration are typically made at which level of task decomposition?
The work package level
The project phase level
The activity level
The deliverable level
Detailed estimates of cost and duration are typically made at the work package level, which represents the lowest level of task decomposition in a project's hierarchical structure. Work packages are manageable units of work that can be assigned to teams or individuals, facilitating accurate planning, execution, and control. Other options such as the project phase level or deliverable level are higher-level components that are too broad for detailed estimating, while the activity level may refer to specific actions but may not provide the necessary context for comprehensive estimation in predictive, plan-based methodologies.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.