CAPM Practice Question
During project execution, a key stakeholder requests frequent updates on project progress, which are not included in the current communication plan. What should the project manager do?
Politely inform the stakeholder that frequent updates are not possible.
Assess the impact of the request and follow the change management process.
Ignore the request and continue with the current communication plan.
Update the communication plan to include the stakeholder's request.