CAPM Practice Question
During project execution, a key stakeholder requests additional updates that are not specified in the communication management plan. What is the best action for the project manager to take?
Provide the additional updates to the stakeholder without changing the communication management plan
Ignore the request as it falls outside the scope of the current plan
Deny the stakeholder's request, explaining that it is not part of the communication management plan
Follow the existing change management process before making any immediate changes.