CAPM Practice Question
During a project's execution, the following data is collected:
- Planned Value (PV): $150,000
- Earned Value (EV): $140,000
- Actual Cost (AC): $160,000
What is the project's cost variance?
$20,000
$10,000
-$10,000
-$20,000
CAPM
Predictive, Plan-Based Methodologies