Labor Day Flash Sale: 30% off Today Only!

7 hours, 42 minutes remaining!

CAPM Practice Question

During a project progress review, a project manager notes that the project was scheduled to complete $70,000 worth of work by this point but has only completed $50,000 worth of work. The actual costs incurred so far are $60,000. Based on this information, which of the following statements accurately describes the project's status?

  • The project is ahead of schedule by $10,000 and over budget by $20,000.

  • The project is ahead of schedule by $20,000 and under budget by $10,000.

  • The project is behind schedule by $10,000 and under budget by $20,000.

  • The project is behind schedule by $20,000 and over budget by $10,000.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot