CAPM Practice Question
During a predictive, plan-based project, a project manager finds that the Earned Value (EV) is $150,000, and the Planned Value (PV) is $130,000 at a certain point in time. What can the project manager conclude about the project schedule?
The project is ahead of schedule by $20,000.
The project is behind schedule by $20,000.
The project is on schedule.
The project is over budget by $20,000.