CAPM Practice Question

During a critical phase of a construction project, unforeseen issues arise that may impact the project timeline. The project team develops a plan to mitigate these issues. To proceed, formal approval is required. Who is responsible for providing this approval to move forward with the proposed plan?

  • The project team

  • The project sponsor

  • The project manager

  • The operations manager

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot