CAPM Practice Question
Becca is a project manager tasked with ensuring that all the work required for the project, and only the work required, is completed. She needs to create a visual representation that organizes the project's deliverables into manageable sections. Which of the following tools should she use?
Project Network Diagram
Gantt Chart
Responsibility Assignment Matrix
Work Breakdown Structure