CAPM Practice Question
At the start of a project, the project manager identifies several stakeholders who may impact the project's outcome. What information should the project manager record in the stakeholder register to ensure effective stakeholder engagement?
Stakeholder's preferred project management methodologies
Stakeholder identification details, influence and impact, and communication requirements
Stakeholder's personal opinions about team members
Stakeholder assigned tasks and responsibilities within the project