As the project manager for a software development project, you need to determine how many team members and what skills are required to complete the project work. Which action should you take?
Wait until the project is underway to see what resources are needed.
Decompose the project deliverables into smaller tasks and estimate the needed resources for each task.
Use the staffing levels from a previous project as a template.
Consult the human resources department to assign available staff to the project.